Case Study

Nuclear Construction

HPC POLAR CRANE DELIVERY

Map-pin South West England

CO-ORDINATED TIER 1 LOGISTICS ENSURE SAFE DELIVERY OF POLAR CRANE AT HPC

We’re proud to be contributing to Britain’s energy security in our role as a Tier 1 contractor at Hinkley Point C (HPC). Osprey coordinates specialist logistics on site, including assets that arrive from overseas. Many milestones have been passed already – including the delivery of two Polar Crane Beams.

Manufacturers can’t send components this large overland, so we bring them in via our Shared Services operations. This way, we can co-ordinate suppliers and suggest the best possible options with a combination of vessels, barges, cranes, SPMTs.

RECOMMENDING THE RIGHT TRANSPORT OPTIONS

  • The Polar Crane Main Beams were brought on site with input from key partners such as APCO, NATCO, and our own Heavy Lift teams here at Osprey. They measure up to 44.77 metres long, and the larger of the two weighs 138,000 kilos. They’re both pivotal to the function and safety of the reactor for its entire, 60-year operating life.
  • During construction, the beams play a crucial role in installing the Reactor Pressure Vessel and other parts of the nuclear steam supply system. Every millimetre of each move needs careful planning, and is signed off by an entire team of engineers, transport, and safety specialists.
  • The first beam came in to the HPC site via from Avonmouth. We factored in all kinds of environmental factors such as weather, tidal conditions in the Bristol Channel and conditions in the River Parrett. We also needed to bear in mind planning constraints for the barges, and to be mindful around local residents’ needs too.
  • To move the Polar Crane Beam across the site, we loaded it onto a specialist, four-file 10-axle self-propelled modular transporter (SPMT). Progress at the right pace is critical to ensuring integrity and safety. This SPMT moved at less than 3 miles per hour during transit, and under fine control during final positioning for unload onto storage supports using the SPMT hydraulics at the construction platform.

COLLABORATION REDUCES RISKS AND COSTS

Universally, lifting is a high-risk activity, but our solution used a combination of transport options to mitigate some of that risk. The direct delivery by SPMT also meant there was at least one less critical lift to perform, which means we’re improving safety, the delivery programme, and overall costs.

Delivering

  • Barge Transport
  • Customs
  • Engineering
  • Heavy Lifting
  • Logistics
  • Project Management
  • RoRo Operations
  • SPMTs
“Our work at Hinkley Point C is a good example of suppliers collaborating, to stay totally focused on a tight schedule.”
Jan Coestsee, Project Manager

See us at work

More case studies

Edgcott Road: 112-Metre Road Bridge

HS2 will build over 11 miles of viaducts and bridges. The Osprey CC-3800 was deployed with a 54-metre boom to provide contract lift services on bridges at Edgcott Road.

Find out more

HPC – RPV installation

RPV DELIVERY - A STATIC, DYNAMIC SOLUTION

At Hinkley Point C, we've developed a RORO solution that delivers oversized assets to site in a new way - increasing productivity across the construction site.

Find out more

Tintagel Bridge installation

Award-winning assets, innovation in action

The new English Heritage walkway at Tintagel is an award-winning installation. Our solution overcame many obstacles associated with overland delivery to this outlying location.

Find out more

Problem-solving for Petrochem

Problem-solving for Petrochem

Minimal downtime for a petrochemical site is critical and our approach kept our operations down to a minimum.

Find out more

PRIORITISING QHSE IN LOGISTICS

Osprey's QHSE team guides all we do

Ellie, one of our QHSE Officers, works specifically on specialist logistics for Hinkley Point C. This puts her at the heart of delivering nuclear success. 

Find out more

RESPONSIVE, RELIABLE PORT SERVICES

Vessel owners trust for Port Services.

RORO, breakbulk, containers, oversized cargoes – along with all the documentation, negotiable Bills of Lading, inventory-linked and non-inventory linked customs entries and supporting services.

Find out more

RESPONSIVE CABLE SERVICES

Safely accelerating offshore project schedules

Knowing our equipment, having in-house expertise, if we can reduce the time taken to deliver a project - we will.

Find out more

NETWORK RAIL, BEWSEY STREET

Jacked lifting solves location problems.

Rail bridges are often in challenging locations. See how we deployed our Enerpac JS250 system to overcome these problems.

Find out more

UPGRADING M4 MOTORWAY BRIDGES

Reducing possession times.

Getting involved early and having the in-house heavy lift equipment to guarantee supply surety - it all makes a difference for projects of this scale.

Find out more

HPC WORLD’S LARGEST STEAM TURBINE

Early planning builds efficiencies into logistics.

Through early contractor engagement and our repeatable Shared Services model, we reduce risks and costs in the delivery of critical assets to large sites.

Find out more

Accreditations and memberships

ISO 9001 logo certificate for Osprey

ISO 14001 Badge for Osprey

QMS ISO 45001 Logo Certificate for Osprey

CPA Collective Mark logo for Osprey

Constructionline Gold Member logo for Osprey

CHAS Accredited Contractor logo for Osprey

LEEA Associate Member Logo for Osprey

RISQS Railway Verified logo for Osprey

ROSPA Award 2022 presented to Osprey

Fit For Offshore Renewables status awarded to Osprey.

Supported by Offshore Wind Growth Partnership logo for Osprey.

logo showing that Osprey is an associate member of CECA Midlands

Logo showing that Osprey is a member of NOF

Osprey is a member of the NIA; the Nuclear Industry Association.

Logo showing that Osprey is a member of BIFA

Logo showing that Osprey is part of Energi Coast