Case Study

Nuclear Construction

HPC WORLD’S LARGEST STEAM TURBINE

Map-pin Bristol

EARLY PLANNING INCREASES EFFICIENCY WHILE DELIVERING COMPONENTS FOR WORLD’S MOST POWERFUL STEAM TURBINE

With the focus on our transition to a low-carbon economy, the supply chain needs partners who deliver trusted efficiency at every stage of a project’s lifecycle. You can see this in our approach to transporting a new low-pressure rotor, weighing 257-tonnes, for the world’s most powerful steam turbine at Hinkley Point C (HPC), in Somerset.

HPC is the first new nuclear power station in the UK for over 20 years. The project is a milestone for the British nuclear power industry. We were appointed by EDF as Tier 1 contractors, to handle and transport all out-of-gauge critical items for the site. Osprey’s nuclear team uses the widest variety of transport at the HPC Terminal –providing a ship-to-shore interface for vessel agency, cargo handling and coordination of onward movement to on-site managed facilities.

PLANNING TO MOVE WORLD’S LARGEST STEAM TURBINE

Working closely with the key project teams at EDF(UK) and GE Power, we built efficiencies into the journey from the outset. The new low-pressure rotor is a critical part of the electrical power production equipment in the turbine hall. It measures 20 meters long, weighs 257 tonnes and houses the largest ‘last stage’ blades ever made at 1.9 metres.

These are one-of-a-kind, multi-million-pound components, and project planning for their transport starts as early as possible. The final set of bladed rotors has 1,216 blades, and the turbine’s rotors will spin at 1,500RPM. This combination will help HPC to generate 3.2GW of CO2-free power for around 6 million homes – a vital part of the UK’s drive towards a zero-carbon future.

  • The rotor’s journey start in Belfort, France, where it had been manufactured and tested by the GE team. From there, it was moved by our partners heavy-lift truck to Neuf-Brisach in the Alsace region of France. We loaded it onto a barge and transported down the Rhine to Rotterdam where it was stored at GE’s consolidation warehouse.
  • We chose a familiar coaster vessel (MV Aasfjord) to transport the LP Rotor from Rotterdam to the UK. This was the first use of innovative Dyneema lashing chains on a major AIL for HPC, which are 85% lighter than the steel alternative.
  • To maximise efficiency again, and use all available under hold deck space, we also brought in three condenser units at the same time.
  • After a two-day journey to Avonmouth, we configured our LG1550 SLDB crane with a 35m boom to give it an overall lifting capacity of 323.4Te, and lifted everything from the vessel onto a 4 file 14 Self Propelled Modular Transporter (SPMT).
  • Once offloaded, all the components were then delivered safely into the bespoke storage facility at HPC. That operation took just under 10 hours, keeping us on schedule as specified in our plans from the outset.

TRUSTED TO DELIVER CRITICAL ASSETS

This inbound journey to Avonmouth is a tried and tested route for Osprey’s HPC team now, but the rotor was a first, and we gained many valuable insights. In short, our early contractor engagement and repeatable Shared Services model reduce risks and costs for everyone delivering critical equipment onto a site.

“It was uneventful, which is just how we like it,” said Daniel Massey, Osprey’s Senior Project Manager. “Critical assets like this need high levels of precision at every stage of the planning process. By working so closely with the core project teams, we could consolidate all the equipment coming into Avonmouth at this point in the project. It’s just one of the ways we deliver value for our clients: we have the cross-sector experience to scrutinise those mammoth project plans and identify opportunities to add value. In this case, it’s good to know we’re not only delivering the components as needed, but as a company, we’re contributing to the low carbon transition in the most hands-on way – this consolidation reduced both the amount of carbon emissions connected to the supply chain and the number of actual journeys involved.”

 

Delivering

  • Customs
  • Engineering
  • LG1550 Crane
  • Project Management
  • SPMTs
“By working closely with the core project teams, we consolidated the equipment coming in – adding value for our clients.”
Daniel Massey, Osprey’s Senior Project Manager

See us at work

More case studies

Edgcott Road: 112-Metre Road Bridge

HS2 will build over 11 miles of viaducts and bridges. The Osprey CC-3800 was deployed with a 54-metre boom to provide contract lift services on bridges at Edgcott Road.

Find out more

HPC – RPV installation

RPV DELIVERY - A STATIC, DYNAMIC SOLUTION

At Hinkley Point C, we've developed a RORO solution that delivers oversized assets to site in a new way - increasing productivity across the construction site.

Find out more

Tintagel Bridge installation

Award-winning assets, innovation in action

The new English Heritage walkway at Tintagel is an award-winning installation. Our solution overcame many obstacles associated with overland delivery to this outlying location.

Find out more

Problem-solving for Petrochem

Problem-solving for Petrochem

Minimal downtime for a petrochemical site is critical and our approach kept our operations down to a minimum.

Find out more

PRIORITISING QHSE IN LOGISTICS

Osprey's QHSE team guides all we do

Ellie, one of our QHSE Officers, works specifically on specialist logistics for Hinkley Point C. This puts her at the heart of delivering nuclear success. 

Find out more

RESPONSIVE, RELIABLE PORT SERVICES

Vessel owners trust for Port Services.

RORO, breakbulk, containers, oversized cargoes – along with all the documentation, negotiable Bills of Lading, inventory-linked and non-inventory linked customs entries and supporting services.

Find out more

RESPONSIVE CABLE SERVICES

Safely accelerating offshore project schedules

Knowing our equipment, having in-house expertise, if we can reduce the time taken to deliver a project - we will.

Find out more

NETWORK RAIL, BEWSEY STREET

Jacked lifting solves location problems.

Rail bridges are often in challenging locations. See how we deployed our Enerpac JS250 system to overcome these problems.

Find out more

HPC POLAR CRANE DELIVERY

Collaboration reduces risks and costs.

We bring multiple specialist logistics' partners together - a great example of this can be seen in the delivery of two Polar Crane Beams in to HPC.

Find out more

UPGRADING M4 MOTORWAY BRIDGES

Reducing possession times.

Getting involved early and having the in-house heavy lift equipment to guarantee supply surety - it all makes a difference for projects of this scale.

Find out more

Accreditations and memberships

ISO 9001 logo certificate for Osprey

ISO 14001 Badge for Osprey

QMS ISO 45001 Logo Certificate for Osprey

CPA Collective Mark logo for Osprey

Constructionline Gold Member logo for Osprey

CHAS Accredited Contractor logo for Osprey

LEEA Associate Member Logo for Osprey

RISQS Railway Verified logo for Osprey

ROSPA Award 2022 presented to Osprey

Fit For Offshore Renewables status awarded to Osprey.

Supported by Offshore Wind Growth Partnership logo for Osprey.

logo showing that Osprey is an associate member of CECA Midlands

Logo showing that Osprey is a member of NOF

Osprey is a member of the NIA; the Nuclear Industry Association.

Logo showing that Osprey is a member of BIFA

Logo showing that Osprey is part of Energi Coast