Case Study

Civil Infrastructure

JLR CABLE-SPAN BRIDGE

Map-pin WHALEY BRIDGE

OUR JOINED-UP APPROACH MEANS EFFICIENT LIFTING AND INSTALLATION

Jaguar Land Rover is expanding its operations with a brand new engineering facility next to its headquarters in Whitely. About half of the 60-acre site at Whitely South will be home to JLR’s new works. We were asked to lift, transport, and prepare the installation of a brand-new bridge over the A45, connecting the new works to the factory’s current footprint.

EARLY PLANNING

Coventry City Council had negotiated a £35m capital plan with the Department for Business, Innovation and Skills that focused on the installation of a new bridge. This cable-span bridge over the A45 links the road network to the site with major arterial routes in the region.

Every site is different, and every piece of critical infrastructure has its challenges. We get involved in the earlier stages of a project like this whenever we can. It’s the Osprey Way of Working. Planning began 12 months before mobilisation, while the installation and move took taking place in the second week in March 2022.

JACKING, MOVING, INSTALLING

The bridge itself is a cable-stayed deck, a common enough configuration these days. But on this occasion, we had the advantage of being able to offer the full range of the services needed – bringing several parts of the project into one scope of work. This lets us deliver a very efficient contracting model, which in itself saves our clients time and money – it’s a joined-up approach to planning and implementation.

  • JACKING: We used a combination of hydraulic climbing jacks and a JS250 jacking system to raise the new bridge, jacking it up by 5m. This took just under 5 days and nights to complete.
  • MOVING: We used 96 axle lines of Self Propelled Modular Trailers (SPMTs) to manoeuvre the bridge from the assembly area to its final position. Our SPMTs can be connected side-by-side and/or head-to-tail, so that they provide a ‘platform on wheels’. They have full rotation steering, which gives us total control over a move – we can manoeuvre critical assets by the smallest increments in any direction allowing us to place the asset with millimetre accuracy.
  • INSTALLING: Finally, our LG1550 mobile crane was used alongside extra SPMTs to upend and install the cable tower, marking our final activity before handing the project over to our client to complete the installation.

We learned a lot in this project, but were delighted we could show a completely ‘joined-up’ approach that delivered efficiencies throughout.

Delivering

  • Cranes
  • Enerpac JS250 Jacking System
  • Engineering
  • Logistics
  • Project Management
  • QHSE
  • SPMTs
"Getting involved from the outset meant we could plan ways to reduce possession times, and to use our equipment in a way that built efficiencies in throughout."
NeilHopkins, Commercial Director

See us at work

More case studies

Edgcott Road: 112-Metre Road Bridge

HS2 will build over 11 miles of viaducts and bridges. The Osprey CC-3800 was deployed with a 54-metre boom to provide contract lift services on bridges at Edgcott Road.

Find out more

HPC – RPV installation

RPV DELIVERY - A STATIC, DYNAMIC SOLUTION

At Hinkley Point C, we've developed a RORO solution that delivers oversized assets to site in a new way - increasing productivity across the construction site.

Find out more

Tintagel Bridge installation

Award-winning assets, innovation in action

The new English Heritage walkway at Tintagel is an award-winning installation. Our solution overcame many obstacles associated with overland delivery to this outlying location.

Find out more

Problem-solving for Petrochem

Problem-solving for Petrochem

Minimal downtime for a petrochemical site is critical and our approach kept our operations down to a minimum.

Find out more

PRIORITISING QHSE IN LOGISTICS

Osprey's QHSE team guides all we do

Ellie, one of our QHSE Officers, works specifically on specialist logistics for Hinkley Point C. This puts her at the heart of delivering nuclear success. 

Find out more

RESPONSIVE, RELIABLE PORT SERVICES

Vessel owners trust for Port Services.

RORO, breakbulk, containers, oversized cargoes – along with all the documentation, negotiable Bills of Lading, inventory-linked and non-inventory linked customs entries and supporting services.

Find out more

RESPONSIVE CABLE SERVICES

Safely accelerating offshore project schedules

Knowing our equipment, having in-house expertise, if we can reduce the time taken to deliver a project - we will.

Find out more

NETWORK RAIL, BEWSEY STREET

Jacked lifting solves location problems.

Rail bridges are often in challenging locations. See how we deployed our Enerpac JS250 system to overcome these problems.

Find out more

HPC POLAR CRANE DELIVERY

Collaboration reduces risks and costs.

We bring multiple specialist logistics' partners together - a great example of this can be seen in the delivery of two Polar Crane Beams in to HPC.

Find out more

UPGRADING M4 MOTORWAY BRIDGES

Reducing possession times.

Getting involved early and having the in-house heavy lift equipment to guarantee supply surety - it all makes a difference for projects of this scale.

Find out more

Accreditations and memberships

ISO 9001 logo certificate for Osprey

ISO 14001 Badge for Osprey

QMS ISO 45001 Logo Certificate for Osprey

CPA Collective Mark logo for Osprey

Constructionline Gold Member logo for Osprey

CHAS Accredited Contractor logo for Osprey

LEEA Associate Member Logo for Osprey

RISQS Railway Verified logo for Osprey

ROSPA Award 2022 presented to Osprey

Fit For Offshore Renewables status awarded to Osprey.

Supported by Offshore Wind Growth Partnership logo for Osprey.

logo showing that Osprey is an associate member of CECA Midlands

Logo showing that Osprey is a member of NOF

Osprey is a member of the NIA; the Nuclear Industry Association.

Logo showing that Osprey is a member of BIFA

Logo showing that Osprey is part of Energi Coast