Case Study

Civil Infrastructure

MANCHESTER AIRPORT BRIDGE INSTALLATION

Map-pin MANCHESTER

SPECIAL LOGISTICS – SAVING TIME IN BRIDGE INSTALLATIONS

One of the biggest challenges for contractors is time: how to complete a job efficiently so that minimum disruption is caused to travellers, commuters, businesses, and bottom lines.

In Manchester, we mitigated the impact of downtime and road closures when we helped to install a new, £6 million pedestrian and cycle bridge over the M56 motorway spur road at Airport City – linking two key parts of the Manchester Airport extension. This was a project for Cleveland Bridge UK, who were working for BCEGI UK Construction – the Principal Contractor, working with Airport City Ltd.

LIFTING AN 81-METRE-LONG SECTION

The bridge itself spans a void of 52.5 meters, although the completed length is 98m. The central section, which we moved into place, was 81m long.

All in all, this structure will link the site to the airport’s transport interchange and terminals, as well as provide direct access for pedestrians and cyclists travelling to and from Wythenshawe and the wider local area. As a critical piece of infrastructure, it needs to last at least one lifetime, if not more and weathering Cor-Ten steel made this a heavy lift in every sense.

COLLABORATING WITH PARTNERS

  • Once the components were assembled and delivered to the site, they were installed using our hydraulic gantry system. By installing the bridge fully assembled, we can reduce downtime on the project instantly.
  • This is a signature skill for Osprey’s bridge logistics teams: our heavy-lift cranes let us load the fully assembled bridge onto SPMTs, having manoeuvred the structure into position, and carrying out self-offloading with minimum disruption.

This was another example of how much is achieved by working better, together. At this location, early planning meant we could consider the less common aspects of a bridge installation project – such as working in the area under flight paths, near airport control towers and radar – and ensure our team provided everything needed to get Cleveland Bridge’s infrastructure into place for BCEGI UK, on time and on budget.

Delivering

  • Engineering
  • Logistics
  • Project Management
  • QHSE
  • SPMTs
"Early planning meant ample time to plan less common aspects of bridge installation – such as working under flight paths."
Neil Hopkins, Commercial Director

See us at work

More case studies

Edgcott Road: 112-Metre Road Bridge

HS2 will build over 11 miles of viaducts and bridges. The Osprey CC-3800 was deployed with a 54-metre boom to provide contract lift services on bridges at Edgcott Road.

Find out more

HPC – RPV installation

RPV DELIVERY - A STATIC, DYNAMIC SOLUTION

At Hinkley Point C, we've developed a RORO solution that delivers oversized assets to site in a new way - increasing productivity across the construction site.

Find out more

Tintagel Bridge installation

Award-winning assets, innovation in action

The new English Heritage walkway at Tintagel is an award-winning installation. Our solution overcame many obstacles associated with overland delivery to this outlying location.

Find out more

Problem-solving for Petrochem

Problem-solving for Petrochem

Minimal downtime for a petrochemical site is critical and our approach kept our operations down to a minimum.

Find out more

PRIORITISING QHSE IN LOGISTICS

Osprey's QHSE team guides all we do

Ellie, one of our QHSE Officers, works specifically on specialist logistics for Hinkley Point C. This puts her at the heart of delivering nuclear success. 

Find out more

RESPONSIVE, RELIABLE PORT SERVICES

Vessel owners trust for Port Services.

RORO, breakbulk, containers, oversized cargoes – along with all the documentation, negotiable Bills of Lading, inventory-linked and non-inventory linked customs entries and supporting services.

Find out more

RESPONSIVE CABLE SERVICES

Safely accelerating offshore project schedules

Knowing our equipment, having in-house expertise, if we can reduce the time taken to deliver a project - we will.

Find out more

NETWORK RAIL, BEWSEY STREET

Jacked lifting solves location problems.

Rail bridges are often in challenging locations. See how we deployed our Enerpac JS250 system to overcome these problems.

Find out more

HPC POLAR CRANE DELIVERY

Collaboration reduces risks and costs.

We bring multiple specialist logistics' partners together - a great example of this can be seen in the delivery of two Polar Crane Beams in to HPC.

Find out more

UPGRADING M4 MOTORWAY BRIDGES

Reducing possession times.

Getting involved early and having the in-house heavy lift equipment to guarantee supply surety - it all makes a difference for projects of this scale.

Find out more

Accreditations and memberships

ISO 9001 logo certificate for Osprey

ISO 14001 Badge for Osprey

QMS ISO 45001 Logo Certificate for Osprey

CPA Collective Mark logo for Osprey

Constructionline Gold Member logo for Osprey

CHAS Accredited Contractor logo for Osprey

LEEA Associate Member Logo for Osprey

RISQS Railway Verified logo for Osprey

ROSPA Award 2022 presented to Osprey

Fit For Offshore Renewables status awarded to Osprey.

Supported by Offshore Wind Growth Partnership logo for Osprey.

logo showing that Osprey is an associate member of CECA Midlands

Logo showing that Osprey is a member of NOF

Osprey is a member of the NIA; the Nuclear Industry Association.

Logo showing that Osprey is a member of BIFA

Logo showing that Osprey is part of Energi Coast