Case Study

Civil Infrastructure

SEACOMBE FERRY TERMINAL

Map-pin Liverpool

NEARSHORE CONSTRUCTION OF SEACOMBE FERRY TERMINAL

The original Seacombe Ferry Terminal dated back to the 1870s. It had suffered in the elements, and the linkspan bridges had reached the end of their operational lifetime – they all needed to be removed and replaced. This was all part of a major investment to keep the services running at Seacombe for many years to come.

Cllr Liam Robinson, Transport and Air Quality Portfolio Holder for the Liverpool City Region Combined Authority: “The installation of these new linkspan bridges is a major milestone in this significant investment at Seacombe Ferry Terminal by the Combined Authority. The Mersey Ferries are an important part of our cultural identity and these works will make sure that they continue to run from Seacombe for many years to come.”

DETAILED PLANNING AND DELIVERY

Due to its age and a lack of original plans, there was very little to show how the linkspan bridge was built, or how it worked. We supported our client for 18 months with marine engineering, naval architecture and project management expertise, developing comprehensive method statements, lift plans, risk assessments and a detailed project schedule for everything within our scope.

This is where we excel. We have the marine, heavy lift and civil engineering expertise in-house, and experience in multiple sectors that let us deliver bespoke, turn-key solutions to our clients’ challenges.

  • Co-ordinated heavy lifting and marine asset removal
  • 18 months of expert, marine engineering support
  • An adjustable mooring, coping with tidal flows
  • Mooring studies supporting infrastructure removal
  • Unique project solution with a floating crane barge

Before deconstruction began, we engineered and delivered an adjustable mooring system that would keep the ferry terminal pontoon in the same place, while the bridges and restraining booms were removed and reinstated. A mooring study explored how the pontoon would behave when we removed sections of the bridge, and what would need implementing to keep our vessels in place and provide moorings for our vessels. We had to contend with limited space, shallow water, vessels transiting the river, tides, and a significant swell.

Deconstruction took place in July, as we did five coordinated lifts over five days, lifting out the restraining booms and old linkspans. This narrow window had to take the Mersey’s significant tidal flow into account, so our teams worked into the night for some of the operations. We then transported these oversized components away from the site, ready for disassembly or refurbishment.

Each bridge weighed more than 125 tonnes, and the refurbished north and south booms weighed 50 tonnes each. Over a four-day period, the new north and south linkspan bridges were moved into place on the quayside using a small fleet of SPMTs and loaded to the barge with our LG1550 Crane. The barge was then towed to site in readiness for the marine lifting operations to take place.

UNIQUE LIFT USING FLOATING CRANE BARGE

This marine lift involved using a floating crane barge to locate and install each bridge section, with a bespoke mooring system that aligned the pieces perfectly between the shoreside terminal and floating pontoon. We consulted on the temporary locating structure that was needed to guide those bridge sections into place.

The tidal phases here only provided short windows for the operation, and it was essential to plan everything down to the last detail: the timing for every phase of the work was critical. The River Mersey has a fast current and the second-highest tidal range in the UK, and the strong swell made for a challenging first lift of the bridge sections in the dark. Even for our crew transfers and safety boats, the swell and the current presented an interesting challenge.

We wanted to make sure our lift work supported the project team’s aspirations for minimum disruption, as much as possible. The installation of new sections for the reconstruction element of the project was completed in October 2021.

Joe Wardle, Osprey – our Project Manager on the Seacombe Ferry Terminal project: “This project has shown what team work and having the right people with the right skills on the job can achieve. The Osprey team worked collaboratively with all involved to ensure the job was completed safely and successfully for our client.”

This project highlighted how valuable our team’s marine engineering and naval architects’ experience is, as we were able to help everyone else involved to find the safest, most practical solution in this challenging environment – site meetings with our client, end clients, pilots, vessel captains, partners and third parties… getting everyone’s input, making sure every aspect of the project was conducted as safely as possible. The new landing stage at the Seacombe Ferry terminal should have a sustainable operation window of least 25 years before any major future maintenance is needed again.

 

Delivering

  • Engineering
  • Floating Crane Barge
  • LG1550 Crane
  • Marine Engineering
  • Mooring Studies
  • Near-shore Construction Logistics
  • Project Management
  • SPMTs
"This was a complex project, excellently managed by Osprey, with the result that everything was delivered to programme and on budget.”
Robin Metcalf, Contracts Manager, SISK

See us at work

More case studies

Edgcott Road: 112-Metre Road Bridge

HS2 will build over 11 miles of viaducts and bridges. The Osprey CC-3800 was deployed with a 54-metre boom to provide contract lift services on bridges at Edgcott Road.

Find out more

HPC – RPV installation

RPV DELIVERY - A STATIC, DYNAMIC SOLUTION

At Hinkley Point C, we've developed a RORO solution that delivers oversized assets to site in a new way - increasing productivity across the construction site.

Find out more

Tintagel Bridge installation

Award-winning assets, innovation in action

The new English Heritage walkway at Tintagel is an award-winning installation. Our solution overcame many obstacles associated with overland delivery to this outlying location.

Find out more

Problem-solving for Petrochem

Problem-solving for Petrochem

Minimal downtime for a petrochemical site is critical and our approach kept our operations down to a minimum.

Find out more

PRIORITISING QHSE IN LOGISTICS

Osprey's QHSE team guides all we do

Ellie, one of our QHSE Officers, works specifically on specialist logistics for Hinkley Point C. This puts her at the heart of delivering nuclear success. 

Find out more

RESPONSIVE, RELIABLE PORT SERVICES

Vessel owners trust for Port Services.

RORO, breakbulk, containers, oversized cargoes – along with all the documentation, negotiable Bills of Lading, inventory-linked and non-inventory linked customs entries and supporting services.

Find out more

RESPONSIVE CABLE SERVICES

Safely accelerating offshore project schedules

Knowing our equipment, having in-house expertise, if we can reduce the time taken to deliver a project - we will.

Find out more

NETWORK RAIL, BEWSEY STREET

Jacked lifting solves location problems.

Rail bridges are often in challenging locations. See how we deployed our Enerpac JS250 system to overcome these problems.

Find out more

HPC POLAR CRANE DELIVERY

Collaboration reduces risks and costs.

We bring multiple specialist logistics' partners together - a great example of this can be seen in the delivery of two Polar Crane Beams in to HPC.

Find out more

UPGRADING M4 MOTORWAY BRIDGES

Reducing possession times.

Getting involved early and having the in-house heavy lift equipment to guarantee supply surety - it all makes a difference for projects of this scale.

Find out more

Accreditations and memberships

ISO 9001 logo certificate for Osprey

ISO 14001 Badge for Osprey

QMS ISO 45001 Logo Certificate for Osprey

CPA Collective Mark logo for Osprey

Constructionline Gold Member logo for Osprey

CHAS Accredited Contractor logo for Osprey

LEEA Associate Member Logo for Osprey

RISQS Railway Verified logo for Osprey

ROSPA Award 2022 presented to Osprey

Fit For Offshore Renewables status awarded to Osprey.

Supported by Offshore Wind Growth Partnership logo for Osprey.

logo showing that Osprey is an associate member of CECA Midlands

Logo showing that Osprey is a member of NOF

Osprey is a member of the NIA; the Nuclear Industry Association.

Logo showing that Osprey is a member of BIFA

Logo showing that Osprey is part of Energi Coast